You are a supervisor for a software development team. You see that your team has added the following phases to the calendar for a new project: planning, design, test, and maintenance. Which phases are missing, and what is their correct order?
Responses
development, implementation, requirements analysis
requirements analysis, implementation, development
requirements analysis, development, implementation
implementation, requirements analysis, development
The correct order and the missing phases are:
- requirements analysis
- design
- development
- implementation
- test
- maintenance
So the missing phases are design and implementation. The correct order would be:
requirements analysis, design, development, implementation, test, maintenance.