You are a supervisor for a software development team. You see that your team has added the following phases to the calendar for a new project: planning, design, test, and maintenance. Which phases are missing, and what is their correct order?

(1 point)
Responses

development, implementation, requirements analysis

development, implementation, requirements analysis

requirements analysis, implementation, development

requirements analysis, implementation, development

requirements analysis, development, implementation

requirements analysis, development, implementation

implementation, requirements analysis, development

The correct order of the phases is: requirements analysis, development, implementation.

So the missing phases are development and implementation.