A contractor estimates it will cost. $2500 to build a deck he then adds 20% onto the cost for labor.

what is the total he will charge for deck?
MUST SHOW WORK

$2500 + (20% of $2500) = $2500 + ($2500 x 0.20) = $2500 + $500 = $3000