20 men dig a trench in 12 days,how many men would be needed to do it in 10 days
1 answer
12 days / 10 days = 12 / 10 = 1.2
1.2 * 20 men = 24 men
You can
ask a new question
or
answer this question
.
Related Questions
20 men can do a piece of work in 24 days. After working for 6 days, an additional number of men are taken to finish the work in
(1) If 10 men can make 12 tables in 6 days, how long would 6 men take to make 36 tables?
(2) A family of 6 ate 240kg bag of rice
It takes 15 men working steadily 4 days to dig the foundation for a new apartment. How many days would it have taken 25 men
Which was a request of Josiah Child’s “Brief Observations Concerning Trade and Interest of Money”?(1 point) Responses the
40 MEN CAN DO A PIECE OF WORK IN 30 DAYS,WORKING 8 HOURS DAILY.IN HOW MANY DAYS WILL 60 MEN FINISH THE WORK WHEN WORKING HOURS
Which of the following best describes the rights of men and women in ancient Jewish society? Select all that apply.
A. Both men
I really dk how to do them,only 2 questions pls anyone help thanks
17)The number of hours N required to dig a certain hole is
Which of the following best describes the rights of men and women in ancient Jewish society? Select all that apply.
A. Both men
if 8 men can do a job in days, what is the percentage increase in number of days required to do the job when 2 men are released?
In the 1800s, it was believed women were good at working on projects to improve the community because (5 points)
women were