Choose the suitable name of these activities or definition from the given names. { Lesser amount of the funds required, Project, Program, None, Maximum funds required}

1. At the time of initiation of project
2. Middle of the project
Bulk of the activity developed
Defined in phased
Placed in life cycle
3. At the time of near to complete the project
4. Unique in Nature
Required limited time scale
Have special purpose
5. Lahore to Islamabad motorway
6. Overhead bridge
7. Underpass to link Road A to Road B
8. Control Traffic flow in Lahore
9. Design to achieve a strategic business objective
10. Provision of faster, save, secure and international traffic facility in Pakistan

1. At the time of initiation of project: Lesser amount of funds required - This activity typically refers to the initial stages of a project where a smaller amount of funds are needed to get the project started.

2. Middle of the project: Bulk of the activity developed - This activity points to the stage in the project where the majority of the work has been completed or developed.

3. At the time of near to complete the project: Maximum funds required - This activity signifies the final stages of the project where maximum funds may be required to wrap up the remaining work and bring the project to completion.

4. Unique in Nature: None - This term does not match any of the given activities. It suggests an activity or project that is distinct or one-of-a-kind.

5. Lahore to Islamabad motorway: Project - This activity refers to the construction of the motorway connecting Lahore to Islamabad, which can be considered a specific project.

6. Overhead bridge: None - This term does not match any of the given activities. It refers to a structure that allows for traffic to pass over an obstacle.

7. Underpass to link Road A to Road B: Project - This activity refers to the construction of an underpass connecting Road A to Road B, which can be considered a specific project.

8. Control Traffic flow in Lahore: Program - This activity involves implementing a program to manage and regulate the flow of traffic in Lahore. A program typically refers to a series of related projects or activities.

9. Design to achieve a strategic business objective: Program - This activity involves designing a program that aligns with a strategic business objective. A program is typically implemented to achieve strategic goals.

10. Provision of faster, safe, secure and international traffic facility in Pakistan: Program - This activity involves a program aimed at providing a traffic facility in Pakistan that is faster, safe, secure, and international in nature.