bcf103

posted by .

your acquisition program expects to award a vehicle production contract in April 2005. The first item from this contract is expected to be delivered in January 2006. The estimated unit cost for each vehicle is $1 million (then-year dollars and the contractor can deliver exactly 3 items per month beginning January 2006.

Respond to this Question

First Name
School Subject
Your Answer

Similar Questions

  1. statistics

    The program plans to acquire a total of 600 end items costing $570 million over a five-year period. The first production contract is to be awarded in FY04. The number of items to be procured (not delivered) each year and their estimated …
  2. Statistics

    Your program plans to acquire a total of 600 end items costing $535 million over a five-year period. The first production contract is to be awarded in FY04. The number of items to be procured (not delivered) each year and their estimated …
  3. Budget

    Your program has an RDT&E-funded project scheduled to start in January 2005 which is expected to take 16 months to complete. The project is expected to cost a total of $16 million (then-year dollars), with cost expected to be incurred …
  4. Math

    Your program has a proposed RDT&E-funded project scheduled to start in January 2005 which is expected to take 16 months to complete. The project is expected to cost a total of $16 million (then-year dollars), with cost expected to …
  5. Finance

    4. Your program plans to acquire a total of 600 end items costing $535 million over a five-year period. The first production contract is to be awarded in FY04. The number of items to be procured (not delivered) each year and their …
  6. Fundamentals of Business Financial Management

    Your program plans to acquire a total of 600 end items costing $570 million over a five-year period. The first production contract is to be awarded in FY04. The number of items to be procured (not delivered) each year and their estimated …
  7. Finance

    Your program has a proposed RDT&E-funded project scheduled to start in January 2015 which is expected to take 16 months to complete. The project is expected to cost a total of $16 million (then-year dollars), with cost expected to …
  8. FUNDAMENTALS OF BUSINESS MGMT

    Your program has a proposed RDT&E-funded project scheduled to start in January 2015 which is expected to take 16 months to complete. The project is expected to cost a total of $16 million (then-year dollars), with cost expected to …
  9. finance

    Your program is planning to award a contract in January 2015 to purchase 100 missiles at an estimated total cost of $100 million (constant FY 2012 dollars). Currently, for Base Year 2012 in the Missile Procurement Appropriation, the …
  10. Business

    Your program plans to acquire a total of 600 end items costing $535 million over a five-year period (five Lots). The first production contract is to be awarded in FY14. The number of items to be procured (not delivered) each year and …

More Similar Questions