Business

posted by .

Assignment for week 5
Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?
ID duration finish to start finish to start additional lag lag
predecessor lag Relationship
A 2 none 0 none 0
B 4 A 0 none 0
C 6 A 0 finish-finish C to F 7
D 8 A 0 none 0
E 18 B 0 finish-finish E & G 9
C 10
F 2 D 0 none
G 5 F 0 Start-start G to H 10
H 5 None 0 none
I 14 E 0 Finish-finish I to J 5
J 15 G,H 0 none 0

  • Business -

    What kind of HELP do you need? You need to be specific when asking questions here.

    If all you do is post your entire assignment, with no evidence of thinking on your part, nothing will happen since no one here will do your work for you. But if you are specific about what you don't understand about the assignment or exactly what help you need, someone might be able to assist you.

Respond to this Question

First Name
School Subject
Your Answer

Similar Questions

  1. College: Modern System Analysis and design

    Construct a Gantt chart and network diagram for a project you are or will be involved in. Choose a project of sufficient depth from work, home, or school. Identify the activities to be completed, determine the sequence of the activities, …
  2. operations research

    4. An R & D project has a list of tasks to be performed whose time estimates are given in the table R & D project Time estimates Activity i - j Activity Name Time (days) To Time (days) tm Time (days) tp 1-2 A 4 6 8 1-3 B 2 3 10 1-4 …
  3. operational management

    Activity Time Predecessor(s) A 3 None B 4 A C 3 B D 5 B E 10 C, D F 3 E G 6 E H 5 G, F Please assist with finding the ES, EF, LS, LF and slack time for ALL activities. also, the critical path?
  4. Applied Decision Methods for Business

    . Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path: Activity Activity Predecessor Time (months) 1 ___ 4 2 ___ 7 3 1 8 4 …
  5. project mgmt

    A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost …
  6. IT

    A project has been defined to contain the following list of activities along with their required times for completion. Activity No. Activity Time (Weeks) Immediate Predecessors 1 Colect requirements 2 - 2 Analyze processes 3 1 3 Analyze …
  7. PM

    You are creating a customer database for Modesto Nuts minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path. How …
  8. PM

    J. Wold. project manager of the Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant …
  9. project management

    REFER TO APPENDIX EXERCISE #4 IN CHAPTER 6 PROJECT MANAGEMENT COMPUTE EARLY, LATE AND SLACK TIMES
  10. math

    Tom Schriber, a director of personnel of Management resources, Inc. is in the process of designing a program that its customers can use in the job finding process. Some of the activites include preparing resumes, writing letters, making …

More Similar Questions