A project has been defined to contain the following list of activities along with their required times for completion.

Activity No.

Activity


Time (Weeks)

Immediate Predecessors


1

Colect requirements

2

-


2

Analyze processes

3

1


3

Analyze data

3

2


4

Design processes

7

2


5

Design data

6

2


6

Design screens

1

3, 4

7

Design reports

5

4, 5

8

Program

4

6, 7

9

Test and document

8

7


10

Install

2

8, 9

a. Draw a network diagram chart for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path.
d. What would happen if activity 6 were revised to take six weeks instead of one week?
e. Construct a Gantt chart for the project defined above.

  1. 👍
  2. 👎
  3. 👁
  1. ssssssssssssssssssssss

    1. 👍
    2. 👎

Respond to this Question

First Name

Your Response

Similar Questions

  1. Educational Technology

    1. Which of the following choices is a strategy that could help with time management? A. Spending most of the day on leisure activities. B. Doing homework in every spare moment. C. Cutting back on sleep. D. Creating a list of

  2. Quantiative Methods

    Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The Co estimates that 150 hours will be required to complete the project. The firm's three graphics designers available

  3. operations research

    4. An R & D project has a list of tasks to be performed whose time estimates are given in the table R & D project Time estimates Activity i - j Activity Name Time (days) To Time (days) tm Time (days) tp 1-2 A 4 6 8 1-3 B 2 3 10

  4. curriculum

    Which of the following is an example of a project-approach activity for a preschool class? A. At 9:00 in the morning every day, half the children in the class do sorting and counting activities while the other half work on an art

  1. improving it without changing its overall meaning

    Ever been assigned to work on a group project for class! Many students dread group projects: because one student typically does most of the work. Unfortunately for some, group work does not end when students leave school, many

  2. social studies

    most of the world's land is used for? A.first-level activities B.second-level activities C.third-level activities D.all three economies activities equall* Whitch of the following is a third-level economy activity. A.hunting

  3. Math

    Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of designing a program that its customers can use in the job-finding process. Some of the activities include preparing resumés, writing

  4. Composition

    Revise the following paragraph, improving it without changing its overall meaning. Pay particular attention to sentence structure. Ever been assigned to work on a group project for class! Many students dread group projects:

  1. English

    Revise the following paragraph, improving it without changing its overall meaning. Pay particular attention to sentence structure. Ever been assigned to work on a group project for class! Many students dread group projects:

  2. Geography

    What are the basic activities in each of the four economic activity levels? My answer: Primary activities involve gathering raw materials such as timber for immediate use or use in the making of a final product. Secondary

  3. quanitative methods

    The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks. (a) What is the probability that the project is finished in 40 weeks or fewer?

  4. Math

    22. Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The company estimates that 150 hours will be required to complete the project. The firm’s three graphics designers

You can view more similar questions or ask a new question.