statistics

1. The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the dues date of the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?

  1. 👍
  2. 👎
  3. 👁
  4. ℹ️
  5. 🚩
  1. Use z-scores.

    Formula:
    z = (x - mean)/sd

    You are looking to solve for x, so fill in the rest of the formula with what you know.

    Find z using z-table (problem gives you percentage). Mean = 80 and standard deviation = 10.

    I hope this will help get you started.

    1. 👍
    2. 👎
    3. ℹ️
    4. 🚩
  2. 88.1594

    1. 👍
    2. 👎
    3. ℹ️
    4. 🚩
  3. the time requested to complete a project is normally distributed with a mean of 80 weeks and standard deviation of 10 weeks. the construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure if finishing by the due date, what due date (project week number) should be negotiated?

    1. 👍
    2. 👎
    3. ℹ️
    4. 🚩
  4. 92.8

    1. 👍
    2. 👎
    3. ℹ️
    4. 🚩

Respond to this Question

First Name

Your Response

Similar Questions

  1. statistics

    The time needed to complete a final examination in a particular college course is normally distributed with a mean of 79 minutes and a standard deviation of 8 minutes. Answer the following questions. Assume that the class has 60

  2. Chemistry

    The first order reaction has a rate constant of 3.0x10^-3 s^-1. The time required for the r eaction to be 75% complete is: 95.8s 201s 231s 462s 41.7s

  3. Quantiative Methods

    Industrial Designs has been awarded a contract to design a label for a new wine produced by Lake View Winery. The Co estimates that 150 hours will be required to complete the project. The firm's three graphics designers available

  4. statistics

    the average number of years a person takes to complete a graduate degree program is 3. the standard deviation is 4 months. Assume the variable is normally distributed. If an individual enrolls in the program, find the probability

  1. operations research

    4. An R & D project has a list of tasks to be performed whose time estimates are given in the table R & D project Time estimates Activity i - j Activity Name Time (days) To Time (days) tm Time (days) tp 1-2 A 4 6 8 1-3 B 2 3 10

  2. Math

    The time needed to complete a final examination in a particular college course is normally distributed with a mean of 83 minutes and a standard deviation of 13 minutes. Answer the following questions. What is the probability of

  3. Math

    Three friends were working on a project. Cindy completed 4/8 of the project. Kim completed 3/8 of the project. Sandy completed 1/8 of the project. How much of the project did they complete all together

  4. IT

    A project has been defined to contain the following list of activities along with their required times for completion. Activity No. Activity Time (Weeks) Immediate Predecessors 1 Colect requirements 2 - 2 Analyze processes 3 1 3

  1. English

    Which of the following is a complete sentence? Never make the same mistake twice. Working on a project that was overdue. One of my friends, who writes beautiful poetry in his spare time. A brand new housing complex full of

  2. jghjkl

    ABC Company has 1,000 employees and wants to increase employee productivity by setting up an internal software applications training program. The training program will teach employees how to use Microsoft software programs such as

  3. project mgmt

    A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated