A firm is planning to set up an assembly line to assemble 40 units per hour. Assume that 57 minutes per hour are productive. The time to perform each task and the tasks preceding each task are as follows:
Task Preceding Task Time to Perform (Min)
A - 0.69
B A 0.55
C B 0.92
D B 0.59
E B 0.70
F B 1.10
G C, D, E 0.75
H G, F 0.43
I H 0.29

Draw a network diagram of precedence relationships. Compute the cycle time per unit in minutes. Compute the minimum number of workstations required to produce 40 units per hour. Balance the assembly line using the longest processing time. Calculate the efficiency of the balanced assembly line.

Microsoft Excel sheet.

  1. 👍
  2. 👎
  3. 👁
  4. ℹ️
  5. 🚩
  1. A ball-bearing assembly firm wants to set up an assembly line which must have an output of 60 units per hour.

    1. 👍
    2. 👎
    3. ℹ️
    4. 🚩

Respond to this Question

First Name

Your Response

Similar Questions

  1. Microeconomics

    Correcting for negative externalities - Regulation versus tradablepermits Suppose the government wants to reduce the total pollution emitted by three local firms. Currently, each firm is creating 4 units of pollution in the area,

  2. Cash Budgeting Question

    Cash Budgeting – Helen Bowers, owner of Helen’s Fashion Designs, is planning to request a line of credit from her bank. She has estimated the following sales forecasts for the firm for parts of 2006 and 2007: May 2006 $180,000

  3. statistic

    . A company is considering installing new machines to assemble its products. The company is considering two types of machines, but it will buy only one type. The company selected eight assembly workers and asked them to use these

  4. Math

    Soundex produces x Model A radios and y Model B radios. Model A requires 15 min of work on Assembly Line I and 10 min of work on Assembly Line II. Model B requires 10 min of work on Assembly Line I and 12 min of work on Assembly

  1. Econ

    Suppose the government wants to reduce the total pollution emitted by three firms in its area. Currently, each firm is creating 4 units of pollution in the area, for a total of 12 pollution units. The government wants to reduce

  2. math

    Jamal got a job working on a assembly line in a toy factory, on the 20th day of work, he assembled 137 toys, he noticed that since he started , every day he assembed 3 more toys then the day before , how many toys did jamal

  3. math

    the cost per hour of running an assembly line in a manufacturing plant is a function of the number of items produced per hour. The cost function is C(x) = 0.28x^2 - 0.7x + 1 where C(x) is the cost per hour in thousands of dollars

  4. Math - Linear Inequalities

    The Wellbuilt Company produces two types of wood chippers, Deluxe and Economy. The Deluxe model requires 3 hours to assemble and ½ hour to paint, and the Economy model requires 2 hours to assemble and 1 hour to paint. The maximum

  1. Economics

    There are three industrial firms in Happy Vally. Initial Cost of Reducing Firm Pollution Level Pollution by 1 unit A 70 units $20 B 80 units $25 C 50 units $10 The government wants to reduce pollution to 120 units, so it gives

  2. marketing

    Which of the following statements regarding marketing strategies is FALSE? A. These strategies require decisions about the specific customers the firm will target and the marketing mix the firm will develop to appeal to that

  3. mangerial econ

    The MorTex Company assembles garments entirely by hand even though a textile machine exists which can assemble garments faster than a human can. Workers cost $50 per day, and each additional laborer can produce 200 more units per

  4. marketing

    Which of the following statements regarding marketing strategies is FALSE? A. These strategies must meet the needs of target customers, and a firm is likely to get a competitive advantage if it just meets needs in the same way as

View more similar questions or ask a new question.