Accounting

posted by .

The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows:
Standard Costs
Fixed overhead (based on 10,000 hours) 3 hours @ $.80 per hour
Variable overhead 3 hours @ $2.00 per hour

Actual Costs
Total variable cost, $18,000
Total fixed cost, $8,000



The amount of the factory overhead controllable variance is:
Answer

A.$2,000 unfavorable

B.$3,000 favorable

C.$0

D.$3,000 unfavorable

  • Accounting -

    1000

  • Accounting -

    A. 2.000 unfavorable

  • Accounting -

    A. 2,000 unfavorable

Respond to this Question

First Name
School Subject
Your Answer

Similar Questions

  1. college

    The Joyner Corporation originally budgeted for $360,000 of fixed overhead. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit. The variable overhead rate was $3 per hour. Actual fixed …
  2. managerial accounting

    The Joyner Corporation originally budgeted for $360,000 of fixed overhead. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit. The variable overhead rate was $3 per hour. Actual fixed …
  3. managerial Accounting

    Smith Co uses a standard cost system for its single product in which variable manufacturing overhead is applied on the basis of direct labor hours. The following information is given: 4 Standard costs per unit: Raw materials (1.5 grams …
  4. accounting

    6. Acme Manufacturing Company estimates factory overhead as a percentage of machine hours. On 1.1.11, Acme estimates total factory overhead of $400,000 for the year, and estimates 20,000 machine hours will be required during the year. …
  5. Accounting

    Original budget for 2009 included $600,000 fixed overhead and $400,000 variable overhead. Labor hours were estimated at 200,000 labor hours. The predetermined overhead rate was $5 per hour. Actual overhead turned out to be $1,100,000. …
  6. Accounting

    Original budget for 2009 included $600,000 fixed overhead and $400,000 variable overhead. Labor hours were estimated at 200,000 labor hours. The predetermined overhead rate was $5 per hour. Actual overhead turned out to be $1,100,000. …
  7. accounting

    The forecast overhead for the current year will be $11,279,512 and that total machine hours will be 160,228 hours. The actual overhead is $7,919,409 and the actual machine hours are 90,509 hours. If the Thomlin Company uses a predetermined …
  8. Accounting

    The St. Augustine Corporation originally budgeted for $360,000 of fixed overhead. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit. The variable overhead rate was $3 per hour. Actual …
  9. Accounting

    The St. Augustine Corporation originally budgeted for $360,000 of fixed overhead. Production was budgeted to be 12,000 units. The standard hours for production were 5 hours per unit. The variable overhead rate was $3 per hour. Actual …
  10. Accounting

    The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: StandardCosts Fixed overhead (based on 10,000 hours) 3 hours @ $.80 per hour Variable overhead3 hours …

More Similar Questions