statistics

posted by .

1. The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the dues date of the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?

  • statistics -

    Use z-scores.

    Formula:
    z = (x - mean)/sd

    You are looking to solve for x, so fill in the rest of the formula with what you know.

    Find z using z-table (problem gives you percentage). Mean = 80 and standard deviation = 10.

    I hope this will help get you started.

  • statistics -

    88.1594

Respond to this Question

First Name
School Subject
Your Answer

Similar Questions

  1. college

    A contractor must pay a $40,000 penalty if construction of an expense home requires more than 16 weeks. He will receive a bonus of $10,000 if the home is completed within 8 weeks. Based on experience with this type of project, the …
  2. statistics

    An obstetrician maintains that preterm babies (gestation less than 37 weeks) have a higher variability of birth weight than do full-term babies (gestation 37-41 weeks). According to the National Vital Statistics Report, Vol. 48, No. …
  3. quanitative methods

    The time required to complete a project is known to be normally distributed with a mean of 44 weeks and a standard deviation of 8 weeks. (a) What is the probability that the project is finished in 40 weeks or fewer?
  4. statistics

    Suppose that the amount of time it takes the IRS to refund to taxpayers is normally distributed with a mean of 12 weeks and a variance of 9. a. What percent of taxpayers should get a refund within 5 weeks?
  5. math proportions

    Five editors finish a project in 3 1/2 weeks. How many editors are needed to complete the same project in 1 1/6 weeks?
  6. math

    Is there some other way I can explain this to my 8th grader. Five editors finish a project in 3 1/2 weeks. How many editors are needed to complete the same project in 1 1/6 weeks
  7. math

    Why wasn't cross multiplication used. Five editors finish a project in 3 1/2 weeks. How many editors are needed to complete the same project in 1 1/6 weeks 5/3.5= x/1.16
  8. Operational Research

    The time required is known to complete a project is known to be normally distributed with a mean of 44 weeks and standard deviations of 8 weeks a) what is the probability that the project is finished in 40 weeks or fewer?
  9. math

    A construction expected a new project from start to finish to take 12 weeks. The crew will work 7 days a week. In how many days will the project be complete. Explain how you could check your answer to be sure it's correct.
  10. English

    "In" can also mean no longer than a particular period of time: 1. Can you finish the job in two weeks?

More Similar Questions