Question 5: (50 points)
E 5-11 Income (loss) recognition; percentage-of-completion and completed contract methods compared LO4
Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2006 and was completed in 2008. The following are a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete
Costs Incurred During Year (As of the End of the Year)
Situation 2006 2007 2008 2006 2007 2008
1 1,500 2,100 900 3,000 900 —
2 1,500 900 2,400 3,000 2,400 —
3 1,500 2,100 1,600 3,000 1,500 —
4 500 3,000 1,000 3,500 875 —
5 500 3,000 1,300 3,500 1,500 —
6 500 3,000 1,800 4,600 1,700 —

Required:
Complete the following table.
Round all answers to the nearest whole dollar. Amounts in parenthesis do not require a minus sign.
Gross Profit (Loss) Recognized
Percentage-of-Completion Completed Contract
Situation 2006 2007 2008 2006 2007 2008
1 $ ____________ $ ____________ $ ____________ $ ____________ $ ____________ $ ____________
2 ____________ ( ____________) ____________ ____________ ____________ ____________
3 ____________ ( ____________) ( ____________) ____________ ( ____________) ( ____________)
4 ____________ ____________ ____________ ____________ ____________ ____________
5 ____________ ( ____________) ____________ ____________ ____________ ____________
6 ( ____________) ( ____________) ( ____________) ( ____________) ( ____________) ( ____________)



________________________________________

  • accounting -

    When you post your question, please tell us what you know about the answer and be specific about how you'd like us to help you.

Respond to this Question

First Name
School Subject
Your Answer

Similar Questions

  1. accounting

    ________________________________________ Question 1: (10 points) E 5-2 Installment sales method; journal entries LO2 Charter Corporation, which began business in 2006, appropriately uses the installment sales method of accounting for …
  2. Accounting

    E 5-11 Income (loss) recognition; percentage-of-completion and completed contract methods compared LO4 Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2006 and was …
  3. accounting

    In 2002, construction work began on a three-year contract at a price of $7,525,000. The firm uses the percentage-of-completion method of financial accounting purposes. The income to be recognized each year is based on the proportion …
  4. Cost accounting

    (Comprehensive) Jackson Construction Company uses a job order costing system. In May 2008, Jackson made a $1,650,000 bid to build a pedestrian overpass over the beach highway in Gulfport, Mississippi. Jackson Construction won the bid …
  5. Intermediate Accounting

    Pan Erickson Construction Company changed from the completed-contract to the percentage-of-compleltion method of accounting for long-term construction contracts during 2008. For tax purposes, the company employs the completed-contract …
  6. accounting

    Cooper Construction Company had a contract starting April 2010, to construct a $9,000,000 building that is expected to be completed in September 2012, at an estimated cost of $8,250,000. At the end of 2010, the costs to date were $3,795,000 …
  7. Cost Accounting

    Please somebody can help with the steps of this problem: Thank you (Comprehensive) Construction Company uses a job order costing system. In May 2008, company made a $1,650,000 bid to build a pedestrian overpass over the beach highway …
  8. Intermediate Accounting

    Island Builders, Inc., has consistently used the percentage-of-completion method of accounting for construction type contracts. During 2004 Island Builders started work on a $9,000,000 fixed-price construction contract that was completed …
  9. Intermediate Accounting

    Total contract price $100,000 Actual costs during 2006 20,000 Estimated remaining costs 40,000 Billed to customer during 2006 30,000 Received from customer during 2006 10,000 16. Under the completed contract method, how much should …
  10. Accounting

    a. IPC purchases real estate in prime locations where an existing theatre chain does not adequately serve the market. After purchasing the real estate, IPC engages a contractor to build a theatre complex. During fiscal 2009, IPC received …

More Similar Questions