Questions LLC
Login
or
Sign Up
Ask a New Question
Unit Learning Curve
Questions (1)
1) It took a contractor 1285 hours to manufacture their first unit of an item. If the contractor expects to achieve a 92% unit
5 answers
asked by
Debra
647 views
Subcategories (1)
Calculation of Manufacturing Hours
Parent Categories (1)
Learning Curve