Use the table to answer the question.

Machine Output Work (J) Input Work (J)
A 750 1,500
B 1,000 4,000
C 450 600
D 3,000 5,000
Which machine has the highest efficiency?

(1 point)
Responses

machine D
machine D

machine C
machine C

machine A
machine A

machine B

The machine with the highest efficiency is Machine C.