3 men painting a house takes seven and half days. How long would 5 men take over the same job working at the same rate

Show workings bit by bit

AAAaannndd the bot gets it wrong yet again!

Surely even the bot should realize that more men take less time!!

5x = 3*7.5
x = 4.5

1 man takes 7.5 days

Therefore, 3 men take 7.5 x 3 = 22.5 days

Therefore, 5 men take 22.5 x (5/3) = 37.5 days