accounting

Evaluate the following project using an IRR criterion, based on an opportunity cost of 10%: CF0 = -6,000, CF1 = +3,300, CF2 = +3,300.
A) Accept, since IRR exceeds opportunity cost.
B) Reject, since opportunity cost exceeds IRR.
C) Accept, since opportunity cost exceeds IRR.
D) Reject, since IRR exceeds opportunity cost.

  1. 👍
  2. 👎
  3. 👁
  1. rsef

    1. 👍
    2. 👎

Respond to this Question

First Name

Your Response

Similar Questions

  1. financ

    All techniques with NPV profile- mutually exclusive projects. Projects A and B, of equal risk. Are alternatives for expanding Rosa Company’s capacity. The firm’s cost of capital is 13%. The cash flows for each project are

  2. smith

    (make a cash flow diagram) A project your firm is considering for implementation has these estimated costs and revenues: an investment cost of $50,000; maintenance costs that start at $5,000 at the end of year (EOY) 1 and increase

  3. economic

    6. The table below is a set of hypothetical production possibilities for a nation. Combination Automobiles(thousands) Beef (thousands of tons) A 0 10 B 2 9 C 4 7 D 6 4 E 8 0 a) Plot the production possibility data. What is the

  4. Math

    A manufacturing firm is thinking of launching a new product. The firm expects to sell $950,000 of the new product in the first year and $1,500,000 each year thereafter. Direct costs including labor and materials will be 45% of

  1. Hospitality

    Calculate the IRR and NPV of this project utilizing a 12% discount rate and a 15% cap rate. Ms. Brown was able to secure a loan for $1,540,000, and an equity investor agreed to invest the remaining $660,000 in exchange for 20%

  2. Economics

    I have created an accurate graph on excel and I believe the answers to the first 2 portions of the question are: The opportunity cost of the first 2,000 automobiles is the inability to produce 1000 tons of beef or we give up 1000

  3. Finance

    Caluating opportunity cost. what is the annual opportunity cost of a checking account that requires a $500 minimum balance to avoid service charges? Assume an interest rate of 3 percent

  4. Investing ( pease help)

    Maxwell Feed & Seed is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's projected IRR can be less than the WACC (and even negative), in which case it will be rejected.

  1. project mgmt

    A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated

  2. Finance

    You are considering opening a new plant. The plant will cost $100 million upfront. After that, it is expected to produce profits of $30 million at the end of every year. The cash flows are expected to last forever. Calculate the

  3. accounting

    . Preference Decisions: NPV vs. IRR vs. Profitability Index Stephens Industries is contemplating four projects: Project P, Project Q, Project R, and Project S. The capital costs and estimated after- tax net cash flows of each

  4. Finance

    Consider the following projects, for a firm using a discount rate of 10%: project NPV IRR PI A $200,000 12.2% 1.04 B $200,001 11% 1.01 C $60,000 10.1% 1.61 D $(235,000) 9% .95 If the projects are independent, which, if any,

You can view more similar questions or ask a new question.