A builder constructed a house according to plans provided by the owner. The contract specified that only Reading brand pipe was to be used in the plumbing. After the house was built, the owner discovered that another brand of pipe had been used. The owner refused to final payment and demanded that the pipe be replaced with Reading pipe, which would have involved major reconstruction. Evidence at trial was that the two brands of pipe were of the same general quality.

The question is "What damages is he owed?"

In this scenario, the owner of the house has discovered that a different brand of pipe was used in the plumbing, despite the contract specifying that only Reading brand pipe should be used. The owner has refused to make the final payment to the builder and is now demanding that the pipe be replaced with Reading pipe, which would require significant reconstruction.

To determine the legal perspective on this situation, we need to consider contractual obligations and potential remedies. Here are the steps to analyze this case:

1. Review the Contract: The first step would be to review the contract between the owner and the builder. Check whether there is a clear provision stating that only Reading brand pipe should be used in the plumbing. Evaluate whether this provision is a condition or a warranty. A condition is an essential term of the contract, while a warranty is a lesser provision.

2. Determine if there was a Breach: If the contract explicitly stated that only Reading brand pipe was required, the use of an alternative brand would likely constitute a breach of contract by the builder. However, if the contract only mentioned Reading brand pipe as a preference or recommendation but did not explicitly require its use, the situation might be different.

3. Assess the Impact of the Breach: Consider whether the use of a different brand of pipe has any substantial impact on the functionality or value of the house. If the two brands of pipe are of the same general quality and the alternative brand does not result in any significant negative consequences, this may affect the owner's claim for major reconstruction or replacement.

4. Explore Remedies: If the breach is established and has a substantial impact, the owner may be entitled to remedies. These may include:

a. Specific Performance: The owner could seek a court order requiring the builder to replace the pipes with Reading brand pipe, despite the potential need for major reconstruction.

b. Damages: If specific performance is impractical or unreasonable, the owner may seek compensation for the difference in value between Reading brand pipe and the alternative brand, along with any other direct losses incurred due to the breach.

5. Consider Mitigation of Damages: The owner has a duty to mitigate their damages. This means they must take reasonable steps to minimize the cost and consequences of the breach. If the owner unreasonably insists on major reconstruction when it is not necessary, they may limit their entitlement to damages.

Ultimately, the resolution of this case will depend on the specific terms of the contract, the impact of the breach, and the applicable laws governing contracts in the relevant jurisdiction. It would be advisable for the owner to consult with a qualified attorney for a thorough assessment and guidance on how to proceed.