Business

Assignment for week 5
Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?
ID duration finish to start finish to start additional lag lag
predecessor lag Relationship
A 2 none 0 none 0
B 4 A 0 none 0
C 6 A 0 finish-finish C to F 7
D 8 A 0 none 0
E 18 B 0 finish-finish E & G 9
C 10
F 2 D 0 none
G 5 F 0 Start-start G to H 10
H 5 None 0 none
I 14 E 0 Finish-finish I to J 5
J 15 G,H 0 none 0

  1. 👍
  2. 👎
  3. 👁
  1. What kind of HELP do you need? You need to be specific when asking questions here.

    If all you do is post your entire assignment, with no evidence of thinking on your part, nothing will happen since no one here will do your work for you. But if you are specific about what you don't understand about the assignment or exactly what help you need, someone might be able to assist you.

    1. 👍
    2. 👎
    👤
    Writeacher

Respond to this Question

First Name

Your Response

Similar Questions

  1. Career Exploration

    Information Technology Quiz 1. Computer user support is another name for: a. customer service b. technical support*** c. network support d. information security 2. Digital designers need what kind of skills? a. network

  2. Career exploration

    1. Information security professionals hack into computer systems. (1 point) True False 2. What kind of network might you have at home? (1 point) LAN WAN wireless intranet 3. Apps are designed by: (1 point) software developers.

  3. College: Modern System Analysis and design

    Construct a Gantt chart and network diagram for a project you are or will be involved in. Choose a project of sufficient depth from work, home, or school. Identify the activities to be completed, determine the sequence of the

  4. PROBABILITY

    FIND THE PROBABILITY OF DRAWING AT LEAST ONE CLUB WHEN YOU DRAW CARDS FROM A STANDAD 52-CARD DECK 52 TIMES; ASSUME YOU REPLACE THE CARD EAC TIMEYOU DRAW, SO THERE ARE ALWAYS 52 CARDS O DRAW FROM. LIST THE APPROPRIE FORMULA, TEN

  1. writing skills

    12. Which sentence contains a prepositional phrase? A. They tried, although they didn't expect to win. [B. Running all the way, he got there early.] C. With the proper help, they'll complete the project early. D. They sang it, and

  2. Statistics

    6)You are given the information that P(A) =0.30 and P(B) =0.40 (a) Do you have enough information to compute P(A or B)? Explain.(events A and B are mutually b) If you know that events A and B are mutually exclusive , do you have

  3. Math

    Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of designing a program that its customers can use in the job-finding process. Some of the activities include preparing resum├ęs, writing

  4. Statistics

    Abia is one of three servers who work at a restaurant that is open from Tuesday to Sunday. Every week the servers randomly draw slips of paper from a hat to decide which two days they will not have to work, in addition to Monday.

  1. history

    I need to someone to write a timeline for me. Assignment Recall that the project requires you to create a timeline that identifies significant events of the Renaissance and Protestant Reformation. Your assignment is to identify at

  2. Finance

    5.3 The manager of a large computer network has developed the following probability distribution of the number of interruptions per day: Interruptions (X) P1X2 0 0.32 1 0.35 2 0.18 3 0.08 4 0.04 5 0.02 6 0.01 a. Compute the

  3. Language Arts Help!!

    10 MS. SMITH: {glossing over his misbehavior and adopting a serious tone as she hands Jason a piece of paper} Yes, ok. So, tell me your plan for the project. Have you consulted this project list yet? You really need to quit

  4. improving it without changing its overall meaning

    Ever been assigned to work on a group project for class! Many students dread group projects: because one student typically does most of the work. Unfortunately for some, group work does not end when students leave school, many

You can view more similar questions or ask a new question.