Assignment for week 5
Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?
ID duration finish to start finish to start additional lag lag
predecessor lag Relationship
A 2 none 0 none 0
B 4 A 0 none 0
C 6 A 0 finish-finish C to F 7
D 8 A 0 none 0
E 18 B 0 finish-finish E & G 9
C 10
F 2 D 0 none
G 5 F 0 Start-start G to H 10
H 5 None 0 none
I 14 E 0 Finish-finish I to J 5
J 15 G,H 0 none 0

  1. 👍 0
  2. 👎 0
  3. 👁 301
asked by Gloria
  1. What kind of HELP do you need? You need to be specific when asking questions here.

    If all you do is post your entire assignment, with no evidence of thinking on your part, nothing will happen since no one here will do your work for you. But if you are specific about what you don't understand about the assignment or exactly what help you need, someone might be able to assist you.

Respond to this Question

First Name

Your Response

Similar Questions

  1. PM

    J. Wold. project manager of the Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant

    asked by kim on August 7, 2013
  2. PM

    You are creating a customer database for Modesto Nuts minor league baseball team. Draw a project network given the information below. Complete the forward and backward pass, compute activity slack, and identify the critical path.

    asked by kim on August 1, 2013
  3. com 135

    Discontinuation of major equipment components for a computer network upgrade will cause a major setback in the installation of the network for a project you are managing. You must provide information about the delay to your

    asked by Adebayo on January 25, 2009
  4. COM 135

    Discontinuation of major equipment components for a computer network upgrade will cause a major setback in the installation of the network for a project you are managing. You must provide information about the delay to your

    asked by Lavender on February 19, 2008
  5. COM 135

    Discontinuation of major equipment components for a computer network upgrade will cause a major setback in the installation of the network for a project you are managing. You must provide information about the delay to your

    asked by Dawn on February 11, 2008
  6. Applied Decision Methods for Business

    . Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path: Activity Activity Predecessor Time (months) 1 ___ 4 2 ___ 7 3 1 8 4

    asked by Zanobia on November 9, 2011
  7. ENG 227

    In this assignment, students will analyze two possible career choices, and then write a formal analytical report effectively presenting a recommendation to pursue one of the careers. This project has two parts: Part 1, the Table

    asked by geniaj on April 5, 2012
  8. College: Modern System Analysis and design

    Construct a Gantt chart and network diagram for a project you are or will be involved in. Choose a project of sufficient depth from work, home, or school. Identify the activities to be completed, determine the sequence of the

    asked by Tank on April 12, 2010
  9. college writing

    Read the following scenario: Discontinuation of major equipment components for a computer network upgrade will cause a major setback in the installation of the network for a project you are managing. You must provide information

    asked by brandy on December 14, 2008
  10. Mike: Project Management

    I've removed your post because you refer to information to which we have no access: "Using the project you created in Unit 1 Individual Assignment, . . ." The rest of your post has a complex set of instructions -- but no

    asked by Ms. Sue on March 3, 2009

More Similar Questions