200 days from March 3 is

a. September 20
b. September 18
c. September 17
d. September 19

my answer is September 19

You're correct. Here are the steps to solve the problem:

1) March 3rd is the 62nd day of the year.
2) Simply add 200 days to 62, and you'll get 262.
3) What is the 262nd day of the year? September 19.

Hope this was helpful! :)

Thanks :)

To determine the date that is 200 days from March 3, you can add 200 days to March 3.

Starting with March 3:
1 day later is March 4
2 days later is March 5
...
...
...
198 days later is September 16
199 days later is September 17
200 days later is September 18

Therefore, the correct answer is September 18, option b.