algebra

posted by .

if ne person can do 25 sqare feet in 4 hours and another in 5 hours how much concrete can they do working together in 8 hours\
\
\

  • algebra -

    rate of 1st person = 25/4 ft^2/h
    rate of 2nd person = 25/5 ft^2/h
    combined rate = (25/4+25/5) or 45/4 ft^2/h

    so area in 8 hrs = 8(45/4) ft^2
    = 90 ft^2

    or

    1st person can do 25 fT2 in 4 hrs, so he can do 50 ft^2 in 8 hrs
    2nd person does 25/5 or 5 ft^2 in 1 hour , so in 8 hours he does 40 ft^2
    50+40 = 90

Respond to this Question

First Name
School Subject
Your Answer

Similar Questions

  1. College Algebra

    It takes Todd 3 hours longer than Tom to paint a 4x5 feet bedroom. Working together, both can complete the job in two hours.How long does it take each one to complete the painting job working alone?
  2. Intermediate Algebra

    A painter can paint a fence in 12 hours working alone. His apprentice who works slower can paint the same fence in 24 hours. How many hours would it take to do the job if they worked together?
  3. Intermediate Algebra

    A painter can paint a fence in 12 hours working alone. His apprentice who works slower can paint the same fence in 24 hours. How many hours would it take to do the job if they worked together?
  4. Quick Math Question

    How do I add time? If a person worked 4 1/2 hours on Monday, 4 1/2 hours on Tuesday and 2 hours on Wednesday, does that add up to 12 hours?
  5. Algebra

    Dorothy and Rosanne are baking cookies for a party. Working alone, Rosanne can finish the cookies in 6 hours. Dorothy can finish them in 8 hours if she is working alone. How long will it take them to bake the cookies if they are working …
  6. Math

    Dorothy and Rosanne are baking cookies for a party. Working alone, Rosanne can finish the cookies in 6 hours. Dorothy can finish them in 8 hours if she is working alone. How long will it take them to bake the cookies if they are working …
  7. Math

    Susie spent 4 1/4 hours on Monday and 3 5/8 hours on Tuesday working on a history project. About how long did she spend working on the project?
  8. maths

    Betty paint twice as fast as Dan. when working together Betty and Dan can paint 2400 square feet in 4 hours,another employee,sue joined their painting team.working together Dan,Betty and Sue can paint 36000 square feet in 3 hours. …
  9. Algebra

    All the members of a construction crew work at the same pace. Four of them working together are able to pour concrete foundations in 32 hours. How many hours would this job take if the number of workers decreased 2 times?
  10. algebra

    All the members of a construction crew work at the same pace. Four of them working together are able to pour concrete foundations in 32 hours. How many hours would this job take if the number of workers: increased 2 times

More Similar Questions

Post a New Question