it takes 7 men 10 days to build a garage.Halfway through building the garage they get some help from 3 people and continue to work at the same rate

a)How long will it take to finish of the garage

b)How long did it take

  • math -

    7*10 man days
    After 5 days or 35 man days
    there are now 10 men to do 35 man days of work
    35/10=3.5 days to finish the work for a total of 8.5 days

Respond to this Question

First Name
School Subject
Your Answer

Similar Questions

  1. physics

    a power = work/time question. A broken car is being pushed to a garage. a) work out the drivers output if he takes 1 hour and 45 mins to push his car 2km with a force of 900N. b) work out the total power output if the driver has to …
  2. Algebra

    7. Marcus can paint a garage in 3 hours. Gina can paint the same garage in 2 hours. How long will it take Marcus and Gina to paint the garage if they work together
  3. algebra

    Anna Can Paint The Garage In 12 Hours. Jenna Can Paint The Same Garage In 7 Hours. How Long Will It Take If They Both Work Together?
  4. Economics

    A city must decide whether to build a downtown parking garage and what rate to charge. It is considering two rates: a flat $1.50-per-hour rate or an all-day rate averaging $1 per hour (based on a $10 daily rate and an average 10-hour …
  5. Math

    A parking garage is changing its parking fees for a week long festival. The function below represents the cost to park in the garage as a function of time (days into the festival). Piece wise c(t) = 10; 0 <= t <= 2 10; 2 < …
  6. math

    A parking garage is changing its parking fees for a week long festival. The function below represents the cost to park in the garage as a function of time (days into the festival). Piece wise c(t) = 10; 0 <= t <= 2 10; 2 < …
  7. math

    A parking garage is changing its parking fees for a week long festival. The function below represents the cost to park in the garage as a function of time (days into the festival). Piece wise c(t) = 10; 0 <= t <= 2 10+ t; 2 < …
  8. math

    A parking garage is changing its parking fees for a week long festival. The function below represents the cost to park in the garage as a function of time (days into the festival). Piece wise c(t) = 10; 0 <= t <= 2 10+ t; 2 < …
  9. Math

    It takes 8 men to build a fence in 9 days so how long it would take 3 men to build the same fence?
  10. math

    The garage you work for as an auto mechanic measures 230 ft. by 150 ft and handles 69 cars. Using the existing garage as a model, how much space would you plan to have in your garage?

More Similar Questions