Post a New Question

math

posted by .

6 builders worked 8 hours a day for 10 days to complete a job.If 8 builders worked 6 hours a day for 3 days,the remaining work has to be completed by 6 builders in 8 days.How many hours does each builder need to work each day?

  • math -

    Presumably 6 builders working 8 hour days accomplish the same work as 8 builders working 6 hour days. After three days of work by 8 builders working 6 hour days, there will still be seven days of work needed, at 48 manhours per day. That is a total of 336 manhours. To complete the remaining work in eight days, you need to perform 42 manhours per day. With six workers, they would have to work 7 hours per day.

Respond to this Question

First Name
School Subject
Your Answer

Similar Questions

  1. Math

    Ok I need help to figure out how to solve this problem 4 working move into town looking for work. A local business offers them 200 hours of work. The catch is, they have to work the same number of hours as they do days. I.E. if they …
  2. math

    ms. gries is an athlete. she is skis every day for 5 days. she skis for 1 1/2 hours for her first day and increases her time by 1 1/4 hours for her next four days. how many hours will she ski on the fifth day?
  3. math

    6 builders worked 8 hours a day for 10 days to complete a job.If 8 builders worked 6 hours a day for 3 days,the remaining work has to be completed by 6 builders in 8 days.How many hours does each builder need to work each day?
  4. Math

    Annie's math test scores are 68 82 82 88 92 98 Her median test score is.. A.30 B.82 C.85 D.88 C?
  5. Math

    Ansgar is writing a novel. He writes seven days a week. On each of those days he write for at least 4 hours but never more than 8 hours. Last week, he wrote for exactly 46 hours. What is the maximum number of days on which he could …
  6. maths

    Three typists working 8 hours a day type a document in 10 days. If only 2 typists are working, how many hours a day should they work to finish the job in 12 days.
  7. math

    trina works after school and on weekends. she always works three days each week. this week she worked 2 3/4 hours on monday, 3 3/5 hours on friday and 5 1/2 hours on saturday. next week she plans to work the same number of hours as …
  8. Math

    Ansgar is writing a novel. He writes seven days a week. On each of those days he writes for at least 4 hours but never more than 8 hours. Last week, he wrote for exactly 46 hours. What is the maximum number of days on which he could …
  9. algebra

    a student worked w hours on tuesday x hours on wednesday y hours on thursday and z hours on friday which algebraic expression represent the average arithmetic mean number of hours per day the student worked for the four days for any …
  10. math

    If a job can be done by 10 workers in 5 hours, the work load is 10(5) = 50 man-hours. If 4 workers is doing the job for 6 hours, the work done is 4(6) = 24 man-hours. A remaining of 50 - 24 = 26 man-hours of work still needs to be …

More Similar Questions

Post a New Question