If it takes 4 people 20 days to build a house, how long does it take 6 people. I know the answer is 15 days, but for the life of me I can't figure out the formula for it.

  • Math -

    20 days are required for 4 people to build a house. So it takes 4*20=80 man-days.
    If we have 6 people, then it should take 80/6=13.3 days to finish the house.

Respond to this Question

First Name
School Subject
Your Answer

Similar Questions

  1. Math

    Hers is another one: 3 people requires 3 weeks and 2 days to do a job. How long would it take for 4 people to do the same job?
  2. algebra

    Here's the problem: It takes Stan 20 days to build a house by himself. When his wife, Brenda, joins him, it takes only 14 days. How long does it take Brenda to build a house on her own?
  3. Algebra

    six people can paint a house in 3 days, how long it would take two people to paint it?
  4. Algebra

    six people can paint a house in 3 days, how long it would take two people to paint it?
  5. math

    it takes 7 men 10 days to build a garage.Halfway through building the garage they get some help from 3 people and continue to work at the same rate a)How long will it take to finish of the garage b)How long did it take
  6. Algebra

    1) Mio can build a large shed in 15 days less than Yuuko can. If they build it together, it would take them 18 days. How long would it take each of them working alone?
  7. Math

    A supply of food lasts 12 people 5 days. A) how long will it last for 1 person?
  8. Math

    The earth takes 365 1/4 days to go around the sun. Mercury takes 3 days less than 1/4 of this time. How many days does Mercury take to go around the sun?
  9. Math

    If it takes 10 people 6 days to do a home improvement, how long would 4 take
  10. Math

    It takes 5 people 3 days to put up a fence?

More Similar Questions