You find a problem in a project. The project has a defined baseline and task progress has been entered for all tasks for the first report period. The ACWP field show the right cost for the work reported, but the BCWP and BCWS fields are zero. what could be the problem?

http://www.eggheadcafe.com/software/aspnet/32119562/bcwp-and-bcws.aspx

The problem you are facing in your project could be related to the Earned Value Management (EVM) calculations. The ACWP (Actual Cost of Work Performed) is reflecting the accurate cost of the work reported. However, the BCWP (Budgeted Cost of Work Performed) and BCWS (Budgeted Cost of Work Scheduled) fields showing zero could indicate a few possible issues. Here are a few potential explanations:

1. Incorrect task assignments or duration: Double-check if all tasks are correctly assigned to resources and have realistic durations. If a task is not assigned or has an incorrect duration, it may impact the BCWP and BCWS calculations.

2. Incorrect baseline: Ensure that a correct baseline has been set for the project. The baseline is used as a reference point for comparing planned work (BCWS) and earned work (BCWP). If the baseline is not set correctly or has been deleted, the BCWP and BCWS fields may show zero.

3. Progress not recorded: Verify if progress has been accurately recorded for the tasks. BCWP represents the value of the work that has been completed, and BCWS represents the value of the work that was scheduled to be completed. If progress is not recorded, both BCWP and BCWS may be zero.

4. Inconsistent project dates: Check if the project start and end dates are correctly set. If the project duration does not match the planned schedule, it can affect the BCWS and BCWP calculations.

To troubleshoot the issue further, review the project setup, task assignments, progress tracking, and baseline settings. It's also helpful to consult the project management software or tools being used, as they may have specific requirements for accurate EVM calculations.