One person can complete a piece of work in 8 days while other person can complete the same work in 4 days(if both works 10 hours per day). how many hours are required to complete the same work if both persons do it combined?

A = 1/8 job/day

B = 1/4 job/day

A + B = 3/8 job /day

which is 8/3 days per job

(8 days/3 jobs) 10 Hours/day

= 80/3 hours/job

= 26 2/3 hours