math

posted by .

If A can do a job in 6 days that V can do in 5 1/2 days and C can do in 2 1/5 days, how long would the job take if A,B, and C were working together?

  • math -

    1/(1/6+1/5.5+1/2.2)
    =1.245 DAYS