The life cycle cost of the BLUEBIRD system is $600 million. The program acquisition cost is $400 million and the development cost is $150 million. There are no facilities costs. What is the procurement cost of the BLUEBIRD system?

$200 million

$150 million

$250 million

$100 million

  • MATH - ,

    250