What is the PROCUREMENT cost of this system?

Cost Types Cost (in millions)
Research/Development $400
Procurement of Prime mission $800
Procurement of support equipment $100
Procurement of Initial Spares $100
Operations & and Support $70,000
Disposal $100

ANWERS! (A). 800 million
(b). 900 milion
(c). 1,400 million
(d) 1,000 million

To determine the procurement cost of the system, we need to sum up the costs associated with procuring the prime mission, support equipment, and initial spares.

According to the provided information, the cost of procurement of the prime mission is $800 million, the cost of procurement of support equipment is $100 million, and the cost of procurement of initial spares is $100 million.

To find the total procurement cost, we add these three costs together:

800 million + 100 million + 100 million = $1,000 million

Therefore, the correct answer is (d) 1,000 million.