What is the PROCUREMENT cost of this system?

Cost Types Cost (in millions)
Research/Development $400
Procurement of Prime mission $800
Procurement of support equipment $100
Procurement of Initial Spares $100
Operations & and Support $70,000
Disposal $100

ANWERS! (A). 800 million
(b). 900 milion
(c). 1,400 million
(d) 1,000 million

To determine the procurement cost of this system, we need to calculate the sum of the costs related to procurement. In this case, we need to add the costs of procurement of the prime mission, support equipment, and initial spares.

The procurement cost is calculated as follows:

Procurement cost = Procurement of Prime mission + Procurement of support equipment + Procurement of initial spares

In this case:

Procurement cost = $800 million + $100 million + $100 million

Therefore, the procurement cost of this system is:

Procurement cost = $1,000 million (or $1 billion)

So, the correct answer is (d) 1,000 million.