What is the PROCUREMENT cost of the below system?

Cost Types Cost (in millions)
Research/Development $400
Procurement of Prime mission $800
Procurement of support equipment $100
Procurement of Initial Spares $100
Operations & and Support $70,000
Disposal $100

ANWERS!
(a) 800 million
(b) 900 milion
(c) 1,400 million
(d) 1,000 million

To determine the procurement cost of the system, we need to add up the costs of procurement of prime mission, support equipment, and initial spares.

Procurement cost = Procurement of Prime mission + Procurement of support equipment + Procurement of Initial Spares

Substituting the given values:

Procurement cost = $800 million + $100 million + $100 million
Procurement cost = $1,000 million

So, the answer is (d) $1,000 million.