What is the PROCUREMENT cost of this system?

Cost Types Cost (in millions)
Research/Development $400
Procurement of Prime mission $800
Procurement of support equipment $100
Procurement of Initial Spares $100
Operations & and Support $70,000
Disposal $100

ANWERS! (A). 800 million
(b). 900 milion
(c). 1,400 million
(d) 1,000 million

To determine the procurement cost of the system, we need to add up the costs specifically associated with procurement. In this case, those costs are:

Procurement of Prime mission: $800 million
Procurement of support equipment: $100 million
Procurement of Initial Spares: $100 million

To calculate the procurement cost, we add these three numbers together:

$800 million + $100 million + $100 million = $1,000 million

Therefore, the correct answer is (d) $1,000 million.