It takes matt 9 hrs longer to build a wall than it takes chris. Working together they can build the wall in 20hrs. how long would it take each working alone to build the wall?

Let's assume that it takes Chris x hours to build the wall.

According to the given information, it takes Matt 9 hours longer to build the wall. Therefore, it would take Matt (x + 9) hours to build the wall alone.

Now, we can determine their rates of work.

Chris's work rate is given by 1/x (wall per hour), while Matt's work rate is 1/(x + 9) (wall per hour).

When they work together, their combined work rate is 1/20 (wall per hour).

Since their rates add up when they work together, we can form the equation:

1/x + 1/(x + 9) = 1/20

To solve this equation, we can find a common denominator:

((x + 9) + x) / (x(x + 9)) = 1/20

Simplifying further:

(2x + 9) / (x^2 + 9x) = 1/20

Cross multiplying:

20(2x + 9) = x^2 + 9x

Expanding:

40x + 180 = x^2 + 9x

Rearranging the equation to bring it to a quadratic form:

0 = x^2 + 9x - 40x - 180

Simplifying:

0 = x^2 - 31x - 180

Now we can solve for x by factoring or using the quadratic formula. Let's use factoring:

0 = (x - 36)(x + 5)

Setting each factor equal to zero:

x - 36 = 0 or x + 5 = 0

Solving for x:

x = 36 or x = -5

Since we cannot have a negative time, x = -5 is not a valid solution.

Therefore, Chris takes 36 hours to build the wall alone, and Matt takes (36 + 9) = 45 hours to build the wall alone.

To solve this problem, we can use the concept of work rates. Let's assign variables to represent the work rates of Matt and Chris.

Let Chris' work rate be represented by C (wall per hour), and let Matt's work rate be represented by M (wall per hour).

Given that it takes Matt 9 hours longer to build the wall than Chris, we can say that Matt's work rate is less than Chris'. So, we have the following relationship: M = C - 1/9 (Matt's work rate is 1/9 less than Chris').

Now, let's consider the combined work rate when they work together. The combined work rate is equal to the sum of their individual work rates: C + M.

We are given that their combined work rate can build the wall in 20 hours. So, we have the equation: (C + M) * 20 = 1 (complete wall).

Substituting the equation for M we found earlier: (C + C - 1/9) * 20 = 1

Simplifying the equation: (2C - 1/9) * 20 = 1

Expanding the equation: 40C - 20/9 = 1

Moving the constant term to the right side: 40C = 1 + 20/9

Simplifying: 40C = 29/9

Dividing both sides by 40: C = (29/9) / 40

Simplifying further: C ≈ 0.0806 (rounded to 4 decimal places)

Now, we can substitute this value of C back into the equation for M: M = C - 1/9

M = 0.0806 - 1/9 ≈ 0.0806 - 0.1111 ≈ -0.0305 (rounded to 4 decimal places)

However, the negative value for M doesn't make sense in this context, so we can assume that there was an error in the given information or the problem itself.

Hence, we cannot determine how long it would take each person, Chris and Matt, to build the wall alone without additional information or by assuming the given information is incorrect.

Chris is x Matt is x+9

2x+9=20
2x=11
x=5.5

Chris = 5.5
Matt= 5.5+9 = 14.5

5.5 +14.5 = 20