Homework Help: Linear Programming and Applications

Posted by Jessie on Thursday, August 23, 2012 at 9:04am.

The production-line employees at GE work four days a week, 10 hours a day. Each day of the
week, (at least) the following numbers of line employees are needed: Monday–Friday, 7 employees; Saturday and Sunday, 3 employees. GE has 11 production-line employees. Formulate an LP that can be used to maximize the number of consecutive days off received by the employees.
For example, a worker who gets Sunday, Monday, and Wednesday off receives two consecutive days off.

Answer this Question

First Name:
School Subject:
Answer:

Related Questions

math - trina works after school and on weekends. she always works three days ...
math linear equations - suppose you earn 5.50/h at a bakery. From your first ...
Math Word problems - an office where 8 secretaries work 8 hours a day 5 days a ...
Technology - Say you have a financial consulting corporation that has four ...
math - Vanessa typically works 8 hours per day in a normal 5 day work week. Last...
Chemistry - You work at a fastr food restaurant 5 days a week, 6 hours a day, ...
math - Vanessa typically works 8 hours per day in a normal 5 day work week. Last...
Math - Ansgar is writing a novel. He writes seven days a week. On each of those ...
math - how do you convert weeks into minutes? my question is, convert 8 weeks ...
Business Law - A business has a backlog of orders and to meet its deadlines, ...

Search
Members