Presumably 6 builders working 8 hour days accomplish the same work as 8 builders working 6 hour days. After three days of work by 8 builders working 6 hour days, there will still be seven days of work needed, at 48 manhours per day. That is a total of 336 manhours. To complete the remaining work in eight days, you need to perform 42 manhours per day. With six workers, they would have to work 7 hours per day.
Related Questions
math - 6 builders worked 8 hours a day for 10 days to complete a job.If 8 ...
math - Tomas can do a job in 4 hours. julia can do the same job in 6 hours. how ...
math - Tiffany worked 9 1/5 hours on Monday and 10 1/4 hours on Tuesday ... how ...
math - May and Bill took 49 hours to complete their History project. They worked...
c++ programming - Solve the following problem. Apply all the steps i.e ...
math - amy is paid time and a half for hours worked in excess of 40 hours and ...
math - 1.a collection of 105 coins consists of 1 peso and 5 pesos. if the total ...
college algebra word problem - Wayne can do a job in 6 hours, while Susan can do...
math 156 - june wants to work for 15 1/2 hours at her part-time job this week. ...
Math (Basic) - "A woman earns 10.00 per hour at her job, but if she works ...
For Further Reading