Posted by GaPeach2909 on Saturday, May 26, 2012 at 7:35pm.

A project has been defined to contain the following list of activities along with their required times for completion.



Activity No.

Activity


Time (Weeks)

Immediate Predecessors



1

Colect requirements

2

-



2

Analyze processes

3

1



3

Analyze data

3

2



4

Design processes

7

2



5

Design data

6

2



6

Design screens

1

3, 4



7

Design reports

5

4, 5



8

Program

4

6, 7



9

Test and document

8

7



10

Install

2

8, 9


a. Draw a network diagram chart for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path.
d. What would happen if activity 6 were revised to take six weeks instead of one week?
e. Construct a Gantt chart for the project defined above.

No one has answered this question yet.

Answer this Question

First Name:
School Subject:
Answer:

Related Questions

project menagement - Put together a proposal for the customer that includes the ...
operations management - project management can be best described as a set of ...
College: Modern System Analysis and design - Construct a Gantt chart and network...
intro tobusiness - objective:increase market share by 5% in telecommunications ...
analysis and design - My project is upgrading a bathroom and this is what I need...
project mgmt - A project has an expected duration of 34 weeks with a critical ...
project management - You find a problem in a project. The project has a defined ...
management - Think of a recently completed group project that you have been ...
operational management - Activity Time Predecessor(s) A 3 None B 4 A C 3 B D 5 B...
chemistry - The time required for the completion of 99.9% of a first order ...

For Further Reading

Search
Members
Community