A project has been defined to contain the following list of activities along with their required times for completion.



Activity No.

Activity


Time (Weeks)

Immediate Predecessors



1

Colect requirements

2

-



2

Analyze processes

3

1



3

Analyze data

3

2



4

Design processes

7

2



5

Design data

6

2



6

Design screens

1

3, 4



7

Design reports

5

4, 5



8

Program

4

6, 7



9

Test and document

8

7



10

Install

2

8, 9


a. Draw a network diagram chart for the activities.
b. Calculate the earliest expected completion time.
c. Show the critical path.
d. What would happen if activity 6 were revised to take six weeks instead of one week?
e. Construct a Gantt chart for the project defined above.

Answer this Question

First Name:
School Subject:
Answer:

Related Questions

College: Modern System Analysis and design - Construct a Gantt chart and network...
project mgmt - A project has an expected duration of 34 weeks with a critical ...
operational management - Activity Time Predecessor(s) A 3 None B 4 A C 3 B D 5 B...
operations research - 4. An R & D project has a list of tasks to be performed ...
math - Tom Schriber, a director of personnel of Management resources, Inc. is in...
Applied Decision Methods for Business - . Construct a Gantt chart and project ...
Finance - The projected revenues and costs that form the basis of the potential ...
240 - Design a series of three presentations/activities for parents and students...
Education - Design a series of three presentations/activities for parents and ...
quanitative methods - The time required to complete a project is known to be ...

Search
Members