The three station work cell illustrated in Figure S7.7, has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2.
Station 1-Machine A-Capacity: 20 units/hr
Station 2-Capacity: 5 units/
Station 3-Capacity: 12 units/hr
a). What is the process of the system?
B) What is the bottleneck time of this week cell?
c) What is the process cycle time?
D) If the firm operates 10 hours per day, 5 days per weekl, what is the weekly capacity of this work cell?
Station 1-Machine B-Capacity: 20 units/hrs

Answer this Question

First Name:
School Subject:
Answer:

Related Questions

operations management - Trucks are required to pass through a weighting station ...
physics - A train starts from station A at 1pm and reaches station B at 3 pm, ...
Math - To chart the movement of a polar bear, scientists attached a radio ...
physics - An express subway train passes through an underground station. It ...
college physics - An express subway train passes through an underground station...
MATH - A company makes three products X, Y and Z. Each product requires ...
MATH- please help! - A company makes three products X, Y and Z. Each product ...
MATH-PLEASE HELPPP!!!! - A company makes three products X, Y and Z. Each product...
math- im really confused! please help!! - A company makes three products X, Y ...
operation management - (01) Why study operations management? (02) What is the ...

Search
Members