3 people take 3 weeks and 2 says, or 20 days, to do the job
so that is 60 workdays.
then 4 people can do the same job in 60/4 or 15 days, which would be 2 weeks and 3 days.
Related Questions
Math - Hers is another one: 3 people requires 3 weeks and 2 days to do a job. ...
math - 1.a collection of 105 coins consists of 1 peso and 5 pesos. if the total ...
Math - A roofing crew can roof a house in 10 hours. If a second crew was added, ...
MATH - A does 8/15 of a work in 8 days and the remaining work is finished with ...
math - A does 8/15 of a work in 8 days and the remaining work is finished with ...
math - A does 8/15 of a work in 8 days and the remaining work is finished with ...
Math - If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do ...
math - Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2...
math - If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do ...
math - A library crew can shelve books in six hours. Another crew can do the job...
For Further Reading