Posted by Karen on Monday, May 18, 2009 at 2:02pm.
combined rate = 1/4 + 1/6 + 1/2 = 11/12
so time taken for working at combined rate = 1/(11/12)
= 12/11 hours
or 1 hour and about 5 minutes
Related Questions
math - Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2...
math - If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do ...
math - if sam can do a job in 4 days that lisa can do in 6 days and tom can do ...
adult education - If Sam can do a job in 4 days that Lisa can do in 6 days and ...
math - vanessa can do a job in 12 days. after she has worked for 4 days, she is ...
chemistry - The disintegration of a radioisotope, such as I-131 to Xe-131, is ...
math - of the following which is the closest approximation to the amount of time...
Algebra - During the last 365 days it was sunny 5 days less than 4 times the ...
English - Soldiers carried several days cold nations. should days chage to a ...
possessive nouns - Soldiers carried several ___ cold rations. Is it A. days B ...
For Further Reading