Wednesday
August 5, 2015

Homework Help: math

Posted by tammy on Wednesday, January 7, 2009 at 6:38am.

Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it?

A. 0.8 days
B. 1.09 days
C. 1.23 days
D. 1.65 days
E. 1.97 days
thanks.

Answer this Question

First Name:
School Subject:
Answer:

Related Questions

More Related Questions

Members