If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it?

A. 0.8 days
B. 1.09 days
C. 1.23 days
D. 1.65 days
E. 1.97 days
thanks.

  • math -

    Do this the same way I did the other one.