Homework Help: math

Posted by tammy on Tuesday, January 6, 2009 at 10:10am.

If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it?

A. 0.8 days
B. 1.09 days
C. 1.23 days
D. 1.65 days
E. 1.97 days
thanks.

Answer this Question

First Name:
School Subject:
Answer:

Related Questions

math - Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2...
math - if sam can do a job in 4 days that lisa can do in 6 days and tom can do ...
adult education - If Sam can do a job in 4 days that Lisa can do in 6 days and ...
Math - If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do ...
math - vanessa can do a job in 12 days. after she has worked for 4 days, she is ...
chemistry - The disintegration of a radioisotope, such as I-131 to Xe-131, is ...
math - of the following which is the closest approximation to the amount of time...
Algebra - During the last 365 days it was sunny 5 days less than 4 times the ...
English - Soldiers carried several days cold nations. should days chage to a ...
possessive nouns - Soldiers carried several ___ cold rations. Is it A. days B ...

For Further Reading

Search
Members
Community